Mobile MRI Parking Pad and Site-Access Requirements

Mobile MRI Parking Pad and Site-Access Requirements

Last reviewed: September 28, 2026.

The facility builds the pad and pays for site preparation. Amber Diagnostics transports the mobile MRI trailer, levels it, connects the utilities, and calibrates the system. An empty parking row is not a pad. The written specification for the quoted coach governs. One pad size is not true for every Amber trailer.

Quick Answer

A mobile MRI trailer needs a level pad, a tractor path, overhead clearance, and utilities at the pad. The facility owns the pad, the electrical work, and the permits. Amber Diagnostics owns transport, placement, leveling, hookup, and calibration. Ask for the pad drawing before you order concrete.

What kind of pad or foundation does a mobile MRI trailer need?

A mobile MRI trailer needs a level pad that can carry the loaded coach on its landing gear and jack pads. Amber Diagnostics rents 1.5T mobile MRI trailers, such as GE and Siemens systems. Length, width, weight, and jack locations change by coach. Your contractor must build from the written pad specification for that unit.

A structural engineer sets thickness, reinforcement, and sub-base from the point loads and the soil. A parking-lot slab is often too thin under the jacks. Some drawings call for a reinforced slab on the order of 6 to 8 inches. That range is a planning note, not an Amber fleet standard. The stamped drawing wins.

The magnet, the table, and the patient lift need a level surface. A slope you can see is already a problem.

The load sits on the jacks. It does not spread like a parked car. A published Amber rental FAQ gives a typical loaded weight of about 30 tons. Some coaches weigh more. Use the number on the drawing.

Concrete is the safer surface for a long rental. Amber Diagnostics also accepts level asphalt when it can carry the coach. Asphalt can rut under jack pads in summer heat. Steel plates can spread the load on a short placement. Asphalt is not banned. It is a poor guess for a long term. Order the drawing before you order concrete. People skip that step and pour the wrong pad.

Leave a safe path for the cryogen vent. The quench pipe must discharge away from doors, air intakes, and places where people stand. If the flat spot puts that vent into a window, pick a different spot.

Put the power feed, the disconnect, and the PACS drop in the pad design. Some coaches also need a water line. The plug is not the same on every coach. Add bollards if cars can hit the skirt.

An existing lot can work if it is level and Amber Diagnostics accepts the surface. A new pad is not ready the morning after the pour.

[IMAGE: Overhead sketch of a parking row with a mobile MRI trailer on a pad. Mark the pad, the approach, the door-side patient zone, the 5-gauss line, and the walk to the building.]

How much space does a mobile imaging unit take up?

Plan three zones. The pad holds the coach. The patient zone holds the lift, the stairs, and the walk. The service zone holds door swing, the power cable, and cryogen access.

Use the table for a first look. Then replace every number with the quoted drawing. These allowances are not a pad for every Amber trailer. Slide-outs change the width after setup.

The mobile MRI rental layout asks for an 8-foot magnetic exclusion zone from the trailer walls. That figure belongs to that layout. Mark the 5-gauss line from the quoted magnet map. Keep pacemaker traffic and ferrous stretchers outside that line.

The lift and the stairs deploy on the passenger side. The path must meet the ADA Standards for Accessible Design. Do not park cars in the service pocket.

Pace a 65 by 22 foot box with cones. If the cones hit a curb or a drain, the spot fails.

Item Planning range What governs
Coach length About 48 to 53 feet Quoted coach drawing
Travel width About 8.5 feet Quoted coach drawing
Height About 13.5 feet Quoted coach drawing
Overhead clearance 14 feet on the route Walk the whole approach
Door-side clearance 10 to 15 feet Quoted layout
Length with tractor 70 to 80 feet Approach, not the pad
Backing space More than 100 feet Site walk
Magnetic exclusion 8 feet on one layout Fringe-field map for that magnet
Cone box About 65 by 22 feet A first look, not a universal pad

Do I need a crane or special access for delivery?

Most Amber mobile MRI rentals do not need a crane. The units stay parked for the full term. A tractor backs the coach onto the pad. The crew drops the landing gear, levels the coach, and detaches the tractor.

You need a crane only when the tractor cannot reach the pad. A courtyard, a podium, a roof, or a lot with no truck path can force that lift. Name that case on the first call. A crane adds lead time and a separate cost. It is not part of a standard tractor drop.

You need 14 feet of overhead clearance on the whole route. Allow more than 100 feet so the driver can back in. A parking deck can fail under the trailer. Get a structural review before you book a deck spot.

Amber Diagnostics coordinates the highway move. You still own the path from the public road to the pad. Clear parked cars before the tractor arrives. A low campus bridge can change the date. The highway permit does not cover the last 200 feet.

Send us your site photos and lot plan. Include the approach and a marked satellite image.

Who handles building the pad and site prep?

The facility builds the pad and pays for site preparation. You hire the concrete contractor and the electrician. You pull the permits. Amber Diagnostics supplies the pad specification, reviews the site, transports the coach, levels it, connects the utilities, and calibrates the system.

Turnkey does not include the pad. On an Amber rental, turnkey means delivery, setup, and service on the trailer and the scanner. It does not mean Amber Diagnostics pours your concrete or files your permit. Read the site-readiness clause before you sign.

The mobile imaging rental pages use the same split. So does the site planning note for a mobile MRI machine.

Work Facility Amber Diagnostics
Pad design and pour Hires the engineer and contractor Supplies the spec for the quoted unit
Electrical service Hires the electrician States volts, phase, and amps on the drawing
PACS network drop IT installs the outlet Connects the coach
Permits Files and pays Does not file
Transport and placement Clears the campus route Tractor delivery
Leveling and calibration Pad and power must be ready Levels, connects, and calibrates
Service during the term Supplies technologists Parts and labor on the rental
Pad removal Agree in the contract Agree in the contract

A concrete contractor builds the pad. An electrician installs the service and the receptacle. Your authority having jurisdiction (AHJ) sets the permits. Amber Diagnostics does not file them.

Ask who pays to remove the pad at the end of the term. Ask who carries the risk if the pad fails under the jacks. Amber Diagnostics can review photos before you spend money on concrete. That review does not replace your contractors. Most sites use their own technologists. A technologist is not in the base rental.

What site requirements does a mobile MRI need overall?

One missing item can delay the first patient as much as a missing pad.

  • Pad: level, load-rated, and built from the quoted coach drawing
  • Footprint: coach, door-side zone, and service clearance marked on the lot
  • Access route: tractor path, 14 feet of overhead clearance, and room to back in
  • Power: dedicated service at the pad, sized from the drawing
  • Network: a weatherproof data drop for PACS
  • Patient access: lift or stairs, an ADA landing, and weather protection
  • Cryogen vent: discharge path clear of doors and air intakes
  • Drainage, lighting, and a snow and ice plan
  • Permits: zoning, temporary structure, electrical, and any state notice
  • Delivery window: a clear route and campus security on the arrival day

Many units use 480-volt three-phase shore power. Amperage is unit-specific. Do not use 150 amps or 200 amps as the number for every Amber trailer. The mobile MRI rental page points you to the coach drawing. A generator is a separate arrangement if the building cannot supply that service. It is not a hidden default.

Confirm whether the quoted coach has a lift, a roll-up door, or a stairwell. Keep 10 to 15 feet clear on the door side.

Get the drawing first. File the permits. Wait for the cure period the engineer sets. Then set the delivery date. Setup usually takes one to three days after power is on. Site readiness is the critical path, not the truck. Typical delivery is two to four weeks after a signed agreement, if a unit is free and the site is ready.

Frequently asked questions

Can a mobile MRI trailer sit on asphalt?

Yes, when the asphalt is level and can carry the loaded coach. Asphalt can rut under jack pads in heat on a long rental. Ask for steel plates if the site walk calls for them.

How long must new concrete cure before delivery?

The structural engineer sets the wait. A new pad is not ready the morning after the pour. A 28-day design-strength figure is a scheduling constraint, not a promise that every pad can take a coach on day 28.

How many parking spaces does a mobile MRI trailer take?

Count your stalls. A coach about 53 feet long covers about six standard stalls. The tractor needs more length on delivery day, then it leaves.

Can the trailer sit on a parking deck?

Only if an engineer says the deck can carry the loaded coach, the jacks, and the tractor. A posted car limit is not that review. If the deck fails, use a ground-level pad.

Does every Amber mobile MRI trailer use the same pad size?

No. Site dimensions are unit-specific. One published coach is about 48 feet long. Amber's rental reference uses about 53 feet as a planning length. Only the quoted drawing counts.

Who pays for the pad if the rental is turnkey?

You do. Turnkey covers transport, placement, leveling, connection, calibration, and service on the scanner and the trailer. It does not cover the pad, the electrical work, or local permits. Put that sentence in the agreement before you sign.

If a tractor can reach a level pad, and the quoted drawing fits that pad, the site can take a mobile MRI trailer. If the pad, the power, or the approach is missing, the fix is schedule and budget. Send your photos and lot plan. Amber Diagnostics will tell you what the quoted coach needs before you order concrete.