A mobile MRI trailer does not have one power number. The shared part is 480V, three-phase power. The amp rating and the connector change with the coach.
A generic mobile MRI guide often states 480V, three-phase, 150A. A Siemens MAGNETOM Aera mobile unit needs 480V, three-phase, 200A, and a Russell Stoll connector. A 150A disconnect does not feed that Aera coach. Hand your electrician the spec sheet for the quoted coach, not a blog number.
Quick Answer
Most mobile MRI trailers use a dedicated 480V, three-phase service. Amp rating is not universal. Generic guides often state 150A. The Amber Diagnostics rental site-prep reference asks for 200A at the pad. A Siemens MAGNETOM Aera mobile unit needs 200A and a Russell Stoll connector. Size the service for the peak load on that coach. Make sure that the number matches the quoted sheet before the electrician bids the work.
Table of Contents
How much power does a mobile MRI unit require?
There is no single amp rating that fits every mobile MRI trailer. Voltage and phase are the stable part. In the United States, the service is 480V, three-phase, 60 Hz, on its own disconnect near the pad.
The amp rating is not stable. A generic mobile MRI guide often states 480V, three-phase, 150A. The Amber Diagnostics rental FAQ uses that 150A sentence and calls it an industry standard. That sentence is too broad to build from. Use it as a warning. Do not use it as a bid.
The current rental site-prep reference asks the facility to supply 480V, three-phase, 200A at the pad. That planning figure is still not a substitute for the coach sheet. The mobile MRI equipment page lists 3-phase, 480V power with a RussellStoll connector. That page does not print one amp number for every coach.
A Siemens MAGNETOM Aera mobile unit needs 200A, and the connector is Russell Stoll. A 150A service misses that unit by 50A. The gap is a different disconnect, a different receptacle rating, and often a different feeder. A receptacle in the wrong series will not mate with the coach cable, even when the voltage is correct.
Field strength does not set the amp rating by itself. The rental reference lists four 1.5T coaches: GE SIGNA Voyager, Siemens MAGNETOM Aera, Siemens MAGNETOM Espree, and GE Signa HDxt. Each coach has its own sheet. We do not assign the Aera 200A Russell Stoll requirement to the other three.
The rental FAQ states that a 3T system is not available in a mobile setting, because the gauss line is wider. This article does not give a 3T trailer amp rating. Do not borrow a 1.5T number for a different coach.
The service must cover the peak, not the idle draw. Gradient amplifiers pull hard in short bursts during a sequence. The magnet, the cold head, and the HVAC draw power the whole time. An onboard chiller adds more load. A breaker sized to the average draw can trip in the middle of a scan.
The magnet also needs power when the room is empty. The cold head keeps the cryogen cold. A long power loss can boil helium off. In the worst case the magnet quenches. Amber Diagnostics rentals include cryogen monitoring. That coverage does not replace a live service at the pad. The rental agreement states who pays if the facility loses power.
A generator is a fallback, not a shortcut. If the site has no 480V, three-phase service, Amber Diagnostics can arrange a dedicated generator as a separate line item. A generator built for 150A is the wrong machine for a 200A Aera coach. Sag or an undersized transformer can abort a scan. The quoted coach sheet sets the voltage tolerance.
| Source | Voltage and phase | Service | Connector |
|---|---|---|---|
| Generic mobile MRI guide | 480V, three-phase | 150A | Often not stated |
| Amber rental FAQ | 480V, three-phase | 150A | Not stated |
| Amber pad reference | 480V, three-phase | 200A at the pad | Match the coach sheet |
| Siemens Aera mobile unit | 480V, three-phase | 200A | Russell Stoll |
| Amber equipment page | 480V, three-phase | Not stated | RussellStoll |
What utility hookups does a mobile MRI trailer need?
Power is the first hookup. It is not the only one. The coach also needs a level pad, a cooling plan, a hard-wired phone line, a hard-wired network drop, and a safe patient path.
Cooling is unit-specific. Some coaches carry a self-contained chiller. The Aera mobile example in the rental file is one of those coaches. Other coaches need a water connection. The site planning note says a unit can run on a pressurized water line, or on a tank that staff refill. Cold weather needs a protected supply line so the pipe does not freeze. Do not order hose and glycol until the sheet names a water loop.
Pad size is unit-specific too. A published rental FAQ describes a typical trailer as about 48 feet long, 8.5 feet wide, and 13.5 feet tall. Loaded weight on that description runs up to about 30 tons. The Aera site note calls for a pad of about 10 by 60 feet. The rental reference asks for about 53 feet of trailer length. It also asks for 14 feet of overhead clearance, and 10 to 15 feet clear on the door side. Tractor approach can exceed 100 feet. Do not average those figures. Use the coach drawing.
The surface must be level concrete or asphalt. A structural engineer sizes the pad for your soil and your code. Hold trucks and forklifts away from the coach. Moving metal can disturb the field.
The mobile MRI equipment page sets an exclusion zone of 8 feet from the trailer walls. That zone is not the 5-gauss line. The 5-gauss line controls pacemaker traffic and ferrous tools, and it can extend past the wall. Put barriers on the real line for that magnet.
Phone and data are facility work. The site planning note says the customer buys the weatherproof outlets. One example is an RJ45 data jack and a Hubbell phone outlet. The next coach can use a different connector. Use a hard-wired drop. Do not plan PACS on a cellular link alone. Start the IT review with the load study.
Who handles the power and utility connections, the facility or the provider?
The facility owns the work up to the trailer. Amber Diagnostics owns the coach and the work on the coach. Put that split in the rental agreement before the electrician mobilizes.
You supply and pay for site preparation, the electrical work, water where the unit needs it, and the local permits. Your side includes the service, any transformer upgrade, the disconnect, the matching receptacle, conduit, and the licensed electrician. A provider technician does not land conductors in your panel. The site planning note says a local qualified electrician makes the shore-power connection.
Amber Diagnostics supplies transport, positioning, leveling, and connection to the utilities you built. After power is on, the scope includes calibration and PACS networking with your IT contact. Scanner and trailer parts and labor are in the rental. Standard service is Monday through Friday, 8:00 a.m. to 9:00 p.m. Holidays are excluded. A hard-down system gets 24/7 coverage. You still supply the network drop and a named IT contact.
Write the gray items into the quote: generator cost, cable ramps, the permit, standby electrician time, and the cost if the service is too small.
Turnkey, on the mobile MRI rental page, means delivery and setup as one job. It does not include a technologist in the monthly rate. Staffing, taxes, facility insurance, physicist testing, and ACR support are separate. The certificate names Amber Diagnostics. Send it to your carrier early.
| Hookup | Who owns it |
|---|---|
| Service, disconnect, receptacle, permits | Facility and a licensed electrician |
| Coach cable and connector | Amber Diagnostics, to the receptacle you built |
| Pad, sized from the coach drawing | Facility |
| Hard-wired phone and network drop | Facility |
| Water, only if the coach sheet names it | Facility |
| Calibration and PACS test after power-on | Amber Diagnostics |
What should I coordinate with my facilities team before delivery?
Start with the coach sheet, then hold one meeting with facilities, biomed, IT, and the electrician. Site readiness is usually the critical path, not equipment availability.
Hand the electrician the sheet, not a generic 150A line. File the permit, build the receptacle, and pass inspection before the truck arrives.
On delivery day the electrician must be on site. A facilities contact must be available. The approach must stay clear for the tractor. Someone on your side signs the power-on record. Setup and calibration usually take one to three days after placement and power connection. A prepared site often starts scans within one week after the trailer arrives. Do not book patients for the morning the trailer arrives.
Typical delivery is two to four weeks after a signed agreement, subject to unit availability. Emergency placement is possible when a staged unit already exists. That window is not a promise. The site still has to be ready.
Copy this list into an email to facilities.
- Coach make, model, and the electrical sheet, attached.
- Voltage, phase, amp rating, and connector from that sheet.
- Panel spare capacity and the run length to the pad.
- Permit filed, inspection date, and the utility date if an upgrade is needed.
- Receptacle type matches the coach connector.
- Pad drawing, overhead clearance, and door-side clearance from the coach sheet.
- Hard-wired phone and network drop, with the IT contact named.
- Cooling plan as an onboard chiller or a water connection, as the sheet says.
- Electrician booked for delivery day.
- First-patient date set after power-on, calibration, and physicist testing.
A fixed CT site plan is a different job. That checklist is about room shielding and a heat exchanger. A mobile MRI coach brings the shield with it. The two plans do not share one power number.
Call 407-438-7847 or use the contact form. Ask for the electrical spec and a site walk before the electrician prices the work.
Frequently asked questions
How much power does a mobile MRI unit require?
A mobile MRI trailer uses 480V, three-phase power on a dedicated disconnect. Amp rating is unit-specific. A generic guide often states 150A. A Siemens MAGNETOM Aera mobile unit needs 200A and a Russell Stoll connector.
Can a mobile MRI run on a generator?
Yes, if the site has no 480V, three-phase service. Amber Diagnostics can arrange a generator as a separate line item. The generator must match the quoted coach. A 150A generator does not feed a 200A Aera coach.
What happens if power is lost?
The cold head must stay on, or the cryogen can boil off. A long outage can quench the magnet. Cryogen monitoring on the rental does not replace power at the pad. The rental agreement states who pays if the facility loses power.
Does a mobile MRI need chilled water?
Some coaches do. Some do not. The Aera mobile example carries a self-contained chiller. Other coaches need a water line or a refillable tank. Read the sheet before you order hose or glycol.
Who pays for the electrical work?
The facility pays for the service, the disconnect, the receptacle, the permits, and the licensed electrician. Amber Diagnostics supplies the coach, the coach-side cable, and the connection to the receptacle you built. A provider technician does not wire your panel.
Is 150A enough for a Siemens Aera mobile unit?
No. That unit needs 200A and a Russell Stoll connector. A 150A service is 50A short. Match the connector as well as the amp rating.
Article, with headline, datePublished, dateModified, and author Bobby Serros. FAQPage for the six questions above. BreadcrumbList. Organization for Amber Diagnostics, Orlando, Florida, service area the continental United States.
Meta title
Mobile MRI Power Needs: 150A Is Not 200A
Meta description
Mobile MRI power is 480V, three-phase. Amp rating changes by coach. A generic guide says 150A. A Siemens Aera unit needs 200A and a Russell Stoll connector.